Cedar Valley College
Parking Lot Construction

CVC will upgrade the S-1 and S-2 parking lots from asphalt to concrete this summer.

The contractor will place fencing around S-1 and the north end of S-2 on Saturday, May 14, 2016. They will begin work on Monday, May 16, 2016. We anticipate the project being complete by Monday, August 29, 2016 in time for the first day of Fall classes.

Beginning Monday, May 16, 2016, parking will be available in the South end of S-1, S-3, W-1 and W-2.


The areas highlighted in “yellow” will be demolished and completed first and those lots will re-open, upon completion. The non-highlighted area in S-1/South parking area will be completed last.
Printable Map